Request a public charging station

You can request a public charging station near your home or work address. The application and placement is free. It can take more than 5 months before a charging station is installed. The municipality does not place charging stations on your own property. You must arrange this yourself.

What do you need to know

  • You have an electric car that can drive at least 45 kilometers electrically
  • You can only request a charging station if there is no existing charging point within 300 meters of your home or work address. On the charging card from MRA-Elektrisch you can see where public charging stations are and are still being installed
  • You can request a public charging station if there is a charging station within 300 meters of your home or work address that is used more than half of the time
  • Only public charging points will be installed that everyone can use
  • The municipality will not install a public charging station if you have your own site where you can park. In that case, the municipality expects you to place a (private) charging station on your own property
  • If you have a parking garage or parking lot with other residents, you can arrange a charging station through the Association of Owners (VvE)
  • Not every place is suitable for the installation of a charging station. The municipality, MRA-E and entrepreneur (charging station operator) look together at the most suitable place
  • When a suitable place has been found for the charging station, we will announce this in The Gooi and Eembode. That's called a traffic order
  • After the announcement of the traffic decree, the grid operator will start preparations for installing the charging station
  • The time between the request for a charging station and the installation of the charging station takes at least 5 months
  • If you have ordered an electric car, send your application for a charging station in advance. A purchase contract or contract with the leasing company is enough to start the application
  • You can also use semi-public charging stations. These are charging stations on private property that everyone can use

Contact

If you have any questions, please call 14 035.

What do you have to do

If you have ordered an electric car, please send your request in advance. A purchase contract or contract with the leasing company is sufficient for the application.

  • You fill a apply for a public charging point at MRA-Electric
  • You will receive a message from MRA-Elektrisch whether a charging station is possible
  • Together with MRA-Elektrisch and the provider of the charging stations, the municipality will look at where a new charging point can be placed in the vicinity of your address.

It takes at least 5 months before the charging station is installed.

What does it cost

Free